Repair of the three MFO and three Sécheron generating sets at Fionnay power station began in 2008. It will be complete in 2012. This repair work is part of a global programme of extraordinary maintenance projects after more than 40 years of service. The scope of the work is as follows:

  • complete renewal of control-command
  • cleaning of rotors
  • repair of bearings and of the lubrication and refrigeration system
  • servicing of exciters

For MFO generating sets, the work also covers repairs to the alternator stator and the replacement of poles.


Special feature

To ensure the operation of alternators over a sustained period of time, the new stators provided for the three MFO units are manufactured to a one-piece design with no stator seal. They are assembled on site by HYDRO Exploitation fitters.